Professional learning guide

Earned Value Management Guide

Learn how planned value, earned value, and actual cost create objective variance, efficiency, and completion forecasts at a consistent status date.

Core concepts

Build the mental model first

Planned Value (PV)
The approved time-phased budget for work scheduled by the status date.
Earned Value (EV)
The approved budgeted value of work objectively completed by the status date.
Actual Cost (AC)
The recorded cost incurred for the completed work by the same status date.
Budget at Completion (BAC)
The approved total budget for the performance measurement baseline.

Formula reference

Calculate—and understand what direction means

MeasureFormulaInterpretation
CPIEV ÷ ACAbove 1.00 is favorable cost efficiency.
SPIEV ÷ PVAbove 1.00 is favorable schedule efficiency.
EACBAC ÷ CPICommon forecast when cost efficiency is expected to continue.
VACBAC − EACPositive forecasts an underrun; negative forecasts an overrun.

Worked reasoning

Status review at month six

01

Situation

CPI is 0.88 and SPI is 0.94, while a major supplier risk remains open.

02

Manager’s approach

Verify progress measurement and actual-cost cut-off first. Investigate the work packages driving variance, update the risk-adjusted forecast, and agree corrective action with owners.

03

Takeaway

Indices are signals, not causes. A sound review connects the signal to root cause, remaining work, risk, and an accountable response.

PMP lens

What to remember in scenario questions

  • Positive CV and SV are favorable.
  • CPI and SPI below 1.00 are unfavorable.
  • Use the EAC formula that matches the scenario assumption.
  • TCPI describes the efficiency required on remaining work.

Common doubts

Questions learners ask

Can hours worked be used as earned value?

Only when the approved progress-measurement method legitimately earns value that way; effort alone is not completed scope.

Why must the status date match?

PV, EV, and AC become misleading when they describe different reporting cut-offs.

Does SPI predict the final date?

Not by itself. Review network logic, milestones, critical path, and remaining duration.

Practice tools

Apply performance & forecasting concepts

View all related tools