Professional learning guide
Earned Value Management Guide
Learn how planned value, earned value, and actual cost create objective variance, efficiency, and completion forecasts at a consistent status date.
By ProjectCalc Editorial Team · Updated October 2026 · 8 min read
Earned value management (EVM) measures project performance by comparing three numbers at a status date: the value of the work planned, the value of the work actually done, and what that work cost. It answers two questions a budget report cannot: are we on schedule, and are we getting what we paid for?
The three numbers behind every EVM calculation
Every EVM measure is built from three values, all in the same currency and all measured at the same status date.
| Term | Also called | What it measures |
|---|---|---|
| Planned value (PV) | BCWS | The approved budget for the work that should be finished by the status date. |
| Earned value (EV) | BCWP | The approved budget for the work that is actually finished. |
| Actual cost (AC) | ACWP | What the finished work has really cost. |
A fourth number, budget at completion (BAC), is the total approved budget. It is the reference for forecasting. EV is the number people get wrong: it is the budgeted value of completed work, not the effort spent and not the money invoiced. If a $10,000 work package is 50% complete by an agreed rule, its EV is $5,000 whatever it has cost so far.
Variances and indices: what is happening now
Variances give the gap in currency. Indices give it as a ratio, which makes projects of different sizes comparable.
| Measure | Formula | Reading |
|---|---|---|
| Cost variance (CV) | EV − AC | Negative: over budget |
| Schedule variance (SV) | EV − PV | Negative: behind schedule |
| Cost performance index (CPI) | EV ÷ AC | Below 1.0: over budget |
| Schedule performance index (SPI) | EV ÷ PV | Below 1.0: behind schedule |
Take PV $50,000, EV $45,000, AC $55,000. CV is −$10,000 and CPI is 0.82: each dollar spent earned about 82 cents of planned value. SV is −$5,000 and SPI is 0.90: 90% of the planned work is done. Try your own figures in the earned value calculator, or work one measure at a time with the CPI and SPI calculator.
Forecasting: where the project is heading
Estimate at completion (EAC) is the forecast of total cost. There is no single formula because the right one depends on why the project is over or under budget. State which you used.
| Situation | EAC formula |
|---|---|
| Past cost performance will continue | BAC ÷ CPI |
| The variance was a one-off; the rest goes to plan | AC + (BAC − EV) |
| Cost and schedule both drive the remaining cost | AC + (BAC − EV) ÷ (CPI × SPI) |
| The original estimate is no longer valid | AC + new bottom-up estimate to complete |
With the figures above and BAC $200,000, the first formula gives $244,444 and the second gives $210,000. That $34,000 spread is the real message: how much of the overrun you expect to repeat. The EAC calculator shows all four side by side.
To-complete performance index
TCPI turns the forecast into a target: the cost efficiency required on the remaining work to hit a goal. TCPI to BAC is (BAC − EV) ÷ (BAC − AC). Here it is 155,000 ÷ 145,000 = 1.07, about 30% better than the 0.82 achieved so far. When the required TCPI is far above your CPI, treat the original budget as at risk. If AC has reached BAC with work remaining, TCPI to BAC is undefined or negative and the budget cannot be met without change. Use the TCPI calculator to test targets.
Making EVM trustworthy in practice
- Fix the baseline first. EVM measures against an approved scope, schedule and budget. If the baseline changes, re-baseline formally and record why.
- Define how progress is earned before work starts: 0/100, 50/50, milestones, or units complete. Avoid subjective percent complete.
- Use one status date for PV, EV and AC. Accruals and unpaid invoices matter: AC should include cost incurred, not only cost paid.
- Read trends, not single points. Plot CPI and SPI over time and ask what changed.
- Pair the numbers with the schedule. A low SPI on non-critical work matters less than a small slip on the critical path.
EVM also fits agile work at the release level, with story points or features as the unit of value. It works best where scope can be broken into measurable pieces with an agreed budget.
Common mistakes
- Counting effort or money spent as progress.
- Mixing data from different cut-off dates.
- Using BAC ÷ CPI automatically, without asking whether the cause will recur.
- Ignoring a CPI that has been below 1.0 for several periods because the latest period looks better.
- Quoting a single index for a project with very different work packages. Check the biggest ones.
Sources
- The Standard for Earned Value Management, Project Management Institute (2019)
- GAO Cost Estimating and Assessment Guide (GAO-20-195G), U.S. Government Accountability Office (2020)
- NASA Earned Value Management (EVM) Implementation Handbook, NASA Office of the Chief Financial Officer (2023)
Quick reference
Key terms, formulas and exam tips
- Planned Value (PV)
- The approved time-phased budget for work scheduled by the status date.
- Earned Value (EV)
- The approved budgeted value of work objectively completed by the status date.
- Actual Cost (AC)
- The recorded cost incurred for the completed work by the same status date.
- Budget at Completion (BAC)
- The approved total budget for the performance measurement baseline.
Formula reference
Calculate—and understand what direction means
| Measure | Formula | Interpretation |
|---|---|---|
| CPI | EV ÷ AC | Above 1.00 is favorable cost efficiency. |
| SPI | EV ÷ PV | Above 1.00 is favorable schedule efficiency. |
| EAC | BAC ÷ CPI | Common forecast when cost efficiency is expected to continue. |
| VAC | BAC − EAC | Positive forecasts an underrun; negative forecasts an overrun. |
Worked reasoning
Status review at month six
Situation
CPI is 0.88 and SPI is 0.94, while a major supplier risk remains open.
Manager’s approach
Verify progress measurement and actual-cost cut-off first. Investigate the work packages driving variance, update the risk-adjusted forecast, and agree corrective action with owners.
Takeaway
Indices are signals, not causes. A sound review connects the signal to root cause, remaining work, risk, and an accountable response.
PMP lens
What to remember in scenario questions
- Positive CV and SV are favorable.
- CPI and SPI below 1.00 are unfavorable.
- Use the EAC formula that matches the scenario assumption.
- TCPI describes the efficiency required on remaining work.
Common doubts
Questions learners ask
Can hours worked be used as earned value?
Only when the approved progress-measurement method legitimately earns value that way; effort alone is not completed scope.
Why must the status date match?
PV, EV, and AC become misleading when they describe different reporting cut-offs.
Does SPI predict the final date?
Not by itself. Review network logic, milestones, critical path, and remaining duration.
Practice tools
Apply performance & forecasting concepts
Earned Value Management
Integrate scope, schedule, and cost performance.
Open calculator →CPI / SPI Calculator
Measure cost and schedule efficiency.
Open calculator →TCPI Calculator
Calculate the efficiency needed to meet a cost target.
Open calculator →Sensitivity Analysis
Identify the assumptions that drive the outcome most.
Open calculator →What-If Analysis
Compare management scenarios before committing.
Open calculator →Project Completion Percentage Calculator
Calculate weighted project completion using completed scope value rather than subjective effort-spent estimates.
Open calculator →Planned Value Calculator
Calculate the budgeted value of work scheduled by the status date for earned value analysis.
Open calculator →Estimate to Complete Calculator
Estimate the remaining cost required to complete project work using the current forecast and cost-efficiency evidence.
Open calculator →