Skip to content

Professional learning guide

Earned Value Management Guide

Learn how planned value, earned value, and actual cost create objective variance, efficiency, and completion forecasts at a consistent status date.

By ProjectCalc Editorial Team · Updated October 2026 · 8 min read

Earned value management (EVM) measures project performance by comparing three numbers at a status date: the value of the work planned, the value of the work actually done, and what that work cost. It answers two questions a budget report cannot: are we on schedule, and are we getting what we paid for?

The three numbers behind every EVM calculation

Every EVM measure is built from three values, all in the same currency and all measured at the same status date.

TermAlso calledWhat it measures
Planned value (PV)BCWSThe approved budget for the work that should be finished by the status date.
Earned value (EV)BCWPThe approved budget for the work that is actually finished.
Actual cost (AC)ACWPWhat the finished work has really cost.

A fourth number, budget at completion (BAC), is the total approved budget. It is the reference for forecasting. EV is the number people get wrong: it is the budgeted value of completed work, not the effort spent and not the money invoiced. If a $10,000 work package is 50% complete by an agreed rule, its EV is $5,000 whatever it has cost so far.

Cumulative cost against time0k50k100k150k200kTimeStatus datePV (plan)AC (actual cost)EV (value earned)
Cumulative cost against time. At the status date, planned value (PV) is above earned value (EV), so the project is behind schedule. Actual cost (AC) is above EV, so it is over budget. The dashed vertical gaps are SV and CV.

Variances and indices: what is happening now

Variances give the gap in currency. Indices give it as a ratio, which makes projects of different sizes comparable.

MeasureFormulaReading
Cost variance (CV)EV − ACNegative: over budget
Schedule variance (SV)EV − PVNegative: behind schedule
Cost performance index (CPI)EV ÷ ACBelow 1.0: over budget
Schedule performance index (SPI)EV ÷ PVBelow 1.0: behind schedule

Take PV $50,000, EV $45,000, AC $55,000. CV is −$10,000 and CPI is 0.82: each dollar spent earned about 82 cents of planned value. SV is −$5,000 and SPI is 0.90: 90% of the planned work is done. Try your own figures in the earned value calculator, or work one measure at a time with the CPI and SPI calculator.

Forecasting: where the project is heading

Estimate at completion (EAC) is the forecast of total cost. There is no single formula because the right one depends on why the project is over or under budget. State which you used.

SituationEAC formula
Past cost performance will continueBAC ÷ CPI
The variance was a one-off; the rest goes to planAC + (BAC − EV)
Cost and schedule both drive the remaining costAC + (BAC − EV) ÷ (CPI × SPI)
The original estimate is no longer validAC + new bottom-up estimate to complete

With the figures above and BAC $200,000, the first formula gives $244,444 and the second gives $210,000. That $34,000 spread is the real message: how much of the overrun you expect to repeat. The EAC calculator shows all four side by side.

To-complete performance index

TCPI turns the forecast into a target: the cost efficiency required on the remaining work to hit a goal. TCPI to BAC is (BAC − EV) ÷ (BAC − AC). Here it is 155,000 ÷ 145,000 = 1.07, about 30% better than the 0.82 achieved so far. When the required TCPI is far above your CPI, treat the original budget as at risk. If AC has reached BAC with work remaining, TCPI to BAC is undefined or negative and the budget cannot be met without change. Use the TCPI calculator to test targets.

Making EVM trustworthy in practice

  • Fix the baseline first. EVM measures against an approved scope, schedule and budget. If the baseline changes, re-baseline formally and record why.
  • Define how progress is earned before work starts: 0/100, 50/50, milestones, or units complete. Avoid subjective percent complete.
  • Use one status date for PV, EV and AC. Accruals and unpaid invoices matter: AC should include cost incurred, not only cost paid.
  • Read trends, not single points. Plot CPI and SPI over time and ask what changed.
  • Pair the numbers with the schedule. A low SPI on non-critical work matters less than a small slip on the critical path.

EVM also fits agile work at the release level, with story points or features as the unit of value. It works best where scope can be broken into measurable pieces with an agreed budget.

Common mistakes

  • Counting effort or money spent as progress.
  • Mixing data from different cut-off dates.
  • Using BAC ÷ CPI automatically, without asking whether the cause will recur.
  • Ignoring a CPI that has been below 1.0 for several periods because the latest period looks better.
  • Quoting a single index for a project with very different work packages. Check the biggest ones.

Sources

Quick reference

Key terms, formulas and exam tips

Planned Value (PV)
The approved time-phased budget for work scheduled by the status date.
Earned Value (EV)
The approved budgeted value of work objectively completed by the status date.
Actual Cost (AC)
The recorded cost incurred for the completed work by the same status date.
Budget at Completion (BAC)
The approved total budget for the performance measurement baseline.

Formula reference

Calculate—and understand what direction means

MeasureFormulaInterpretation
CPIEV ÷ ACAbove 1.00 is favorable cost efficiency.
SPIEV ÷ PVAbove 1.00 is favorable schedule efficiency.
EACBAC ÷ CPICommon forecast when cost efficiency is expected to continue.
VACBAC − EACPositive forecasts an underrun; negative forecasts an overrun.

Worked reasoning

Status review at month six

01

Situation

CPI is 0.88 and SPI is 0.94, while a major supplier risk remains open.

02

Manager’s approach

Verify progress measurement and actual-cost cut-off first. Investigate the work packages driving variance, update the risk-adjusted forecast, and agree corrective action with owners.

03

Takeaway

Indices are signals, not causes. A sound review connects the signal to root cause, remaining work, risk, and an accountable response.

PMP lens

What to remember in scenario questions

  • Positive CV and SV are favorable.
  • CPI and SPI below 1.00 are unfavorable.
  • Use the EAC formula that matches the scenario assumption.
  • TCPI describes the efficiency required on remaining work.

Common doubts

Questions learners ask

Can hours worked be used as earned value?

Only when the approved progress-measurement method legitimately earns value that way; effort alone is not completed scope.

Why must the status date match?

PV, EV, and AC become misleading when they describe different reporting cut-offs.

Does SPI predict the final date?

Not by itself. Review network logic, milestones, critical path, and remaining duration.

Practice tools

Apply performance & forecasting concepts

View all related tools