TCPI Calculator
To-Complete Performance Index analysis with earned value management and project forecasting
To-Complete Performance Index calculation
Future performance requirements
Resource utilization assessment
Performance improvement guidance
Earned Value Management Parameters
Uses original budget as target (ideal performance scenario)
Budgeted cost of work scheduled
Budgeted cost of work performed
Actual cost of work performed
Total planned budget
What is the To-Complete Performance Index (TCPI)?
The To-Complete Performance Index is a forward-looking earned value metric that tells you the cost performance efficiency you must maintain for the remainder of the project to meet a specific financial target. Unlike CPI, which measures how efficiently you have been performing up to now, TCPI measures how efficiently you need to perform from this point forward. It is the financial equivalent of asking, "How hard do we have to pedal to reach our destination on time and on budget?"
TCPI is one of the PMP exam's most frequently tested earned value concepts because it bridges the gap between historical performance analysis and future planning. When your project is over budget, TCPI tells you exactly how much efficiency improvement is required to recover. When the required TCPI is unrealistically high -- typically above 1.25 -- it signals that the original budget target is no longer achievable and that a revised Estimate at Completion should be used instead.
The metric can be calculated against two different targets: the original Budget at Completion (BAC) for an optimistic scenario, or the revised Estimate at Completion (EAC) for a realistic scenario. Understanding both variants and when to use each is a core competency that the PMBOK Guide emphasizes within the Control Costs process.
TCPI Formula Explained
The numerator (BAC - EV) represents the remaining work measured in budgeted terms -- the value of work you still need to complete. The denominator represents the remaining financial resources available. When targeting the original BAC, your remaining budget is (BAC - AC). When targeting a revised EAC, your remaining budget is (EAC - AC). Both formulas divide remaining work by remaining budget to calculate the required efficiency rate.
A TCPI of exactly 1.0 means you need to perform at precisely your planned efficiency for the rest of the project. A TCPI below 1.0 means you have more budget remaining than work to do -- you can actually afford to be less efficient and still meet your target. A TCPI above 1.0 means you must improve your cost efficiency above the original plan. A TCPI above 1.25 is generally considered a red flag, indicating that the financial target is probably unachievable without extraordinary measures.
Step-by-Step Guide to Calculating TCPI
Collect your earned value data: Budget at Completion (BAC), Earned Value (EV), Actual Cost (AC), and if using the EAC-based formula, your current Estimate at Completion (EAC).
Choose your target: use BAC if management insists on the original budget, or use EAC if a revised forecast has been accepted. The calculator above lets you toggle between both methods.
Calculate remaining work: BAC minus EV. This tells you the budgeted value of work still outstanding.
Calculate remaining budget: BAC minus AC (for BAC-based) or EAC minus AC (for EAC-based). This is the financial runway left.
Divide remaining work by remaining budget to get TCPI. Compare the result against 1.0. If TCPI exceeds 1.25, escalate to management with a recommendation to revise the budget rather than expect the team to achieve an unrealistic efficiency target.
Real-World TCPI Example
Scenario: Commercial Building Construction
Budget at Completion (BAC): $2,000,000
Earned Value to date (EV): $800,000 (40% complete)
Actual Cost to date (AC): $950,000
Remaining work: $2,000,000 - $800,000 = $1,200,000
Remaining budget: $2,000,000 - $950,000 = $1,050,000
TCPI (BAC-based) = $1,200,000 / $1,050,000 = 1.143. The team must work at 114.3% of planned efficiency to complete within the original budget. This is achievable with focused corrective action but requires immediate intervention. If management approves a revised EAC of $2,200,000, the TCPI drops to $1,200,000 / $1,250,000 = 0.96, meaning the team can perform slightly below plan and still meet the revised target.
Common Mistakes to Avoid with TCPI
- Confusing TCPI with CPI -- CPI measures past performance, while TCPI measures the future efficiency required. A low CPI with a high TCPI means you have been inefficient and must now overcompensate. These are complementary metrics, not interchangeable ones.
- Using BAC-based TCPI when the budget is clearly unrealistic -- If your TCPI based on BAC exceeds 1.25, continuing to use it gives a false sense of possibility. Switch to the EAC-based TCPI for a more meaningful performance target.
- Not comparing TCPI against CPI -- The gap between your current CPI and required TCPI tells you how much performance must improve. If your CPI is 0.80 and your TCPI is 1.20, the team needs to improve efficiency by 50% relative to current performance. That context is critical for management decisions.
- Calculating TCPI too early in the project -- When the project is only 10-15% complete, TCPI can be volatile and misleading. It becomes a more reliable indicator after 20-25% completion when enough performance data exists.
- Ignoring the management implications -- A TCPI above 1.0 is not just a number; it signals that corrective action is needed. Failing to act on a high TCPI converts a recoverable situation into an unrecoverable budget overrun.
- Forgetting that TCPI is a cost-only metric -- TCPI addresses cost efficiency exclusively. It does not account for schedule performance. Use SPI and TCPI together for a complete picture of what the team must achieve going forward.
PMP Exam Tips for TCPI
The PMP exam tests TCPI from two angles: formula calculation and interpretation. You should be able to compute TCPI from given BAC, EV, and AC values, and also determine whether a given TCPI value represents a positive or concerning situation. The exam loves to present a scenario where TCPI based on BAC is unachievable (above 1.25) and ask what the project manager should do -- the answer is typically to recalculate TCPI based on the revised EAC.
Pay attention to the interplay between TCPI and CPI. The exam may present a situation where current CPI is 0.85 and TCPI based on BAC is 1.30. The implication is that the team needs to improve efficiency by more than 50%, which is unrealistic. The correct course of action is to recommend revising the budget and using EAC-based TCPI instead. This demonstrates both technical competence and practical judgment.
Finally, know that TCPI is conceptually the inverse of CPI in certain ways. Where CPI tells you how efficiently you have been working (EV/AC), TCPI tells you how efficiently you must work going forward (remaining work / remaining budget). The exam may phrase questions around this relationship, asking you to identify which metric is backward-looking versus forward-looking.
Related Calculators
- Use this when
- Use this at a regular status date after the scope, schedule, and cost baselines have been approved and progress can be measured objectively.
- Prepare
- Confirm the status date and bring consistent planned value, earned value, actual cost, and budget-at-completion data from the same reporting period.
- Decision supported
- Use the signal to decide whether to investigate variance, revise the forecast, protect contingency, or initiate corrective action.
Practitioner guidance and limitations
Interpret and act
Focus on trend and materiality, not a single isolated number. Pair indices and variances with milestone health, risk exposure, and the remaining work.
Professional caution
EVM is only as reliable as the baseline and progress-measurement method. Do not mix data from different cut-off dates or count effort as earned scope.
Learn the topic: concept, PMP lens, and common mistakes
Core concept
Earned Value Management integrates approved scope, schedule, and actual cost at one status date. Earned value represents budgeted value of completed scope—not effort consumed or invoices paid.
Professional application
Use trends in variance and efficiency indices to identify the cause, update the forecast, and agree corrective action while useful options still remain.
PMP exam and practice lens
Remember the direction of the core measures: positive CV and SV are favorable; CPI and SPI above 1.00 are favorable. Select the EAC or TCPI formula that matches the scenario assumptions.
Common mistakes
- Mixing PV, EV, and AC from different reporting cut-off dates
- Claiming progress without objective completion rules
- Treating an index as the explanation instead of investigating root cause
Before you trust the result
- Confirm one status date and consistent units.
- Retain the input source, owner, and confidence.
- Sense-check the result against an independent benchmark.
- Record the decision, action owner, and review date.
Related practice tools
How the TCPI calculation works
The to-complete performance index is the cost efficiency the team must achieve on the remaining work to finish within a target budget.
Formulas
| Measure | Formula | How to read it |
|---|---|---|
| TCPI to BAC | TCPI = (BAC − EV) ÷ (BAC − AC) | Efficiency needed to finish on the original budget. |
| TCPI to EAC | TCPI = (BAC − EV) ÷ (EAC − AC) | Efficiency needed to finish on a revised forecast. |
What the terms mean
- PV
- Planned value: budgeted cost of the work scheduled to be done by the status date
- EV
- Earned value: budgeted cost of the work actually completed
- AC
- Actual cost: what the completed work has really cost
- BAC
- Budget at completion: total approved budget
Worked example
Inputs
- PV = $50,000
- EV = $45,000
- AC = $55,000
- BAC = $200,000
Steps
- Work remaining = $200,000 − $45,000 = $155,000
- Budget remaining = $200,000 − $55,000 = $145,000
- TCPI = $155,000 ÷ $145,000 = 1.07
Result: The team must earn 1.07 of value per dollar from now on, compared with 0.82 so far. That is roughly 30% better than the efficiency achieved so far, so BAC is unlikely to be met without a change in performance, scope or funding.
How to interpret the result
| If you see | It usually means |
|---|---|
| TCPI ≈ 1.0 | Plan is achievable at the current pace. |
| TCPI > 1.1 | Hard to achieve. Consider a revised EAC. |
| TCPI > 1.2 | Very unlikely without scope or funding changes. |
| BAC − AC ≤ 0 | The budget is spent. TCPI to BAC is undefined or negative and cannot be met. |
Common mistakes
- Targeting BAC after the budget is already exhausted.
- Ignoring that TCPI assumes the remaining work is as well estimated as the work done.
Frequently asked questions
What is a good TCPI?
Close to 1.0 is good. Values above about 1.1 mean the remaining work must be done noticeably more efficiently than the work so far.
When should I use TCPI to EAC?
Use it after the project has accepted that BAC is out of reach and a new EAC is the target.
Sources and method
- The Standard for Earned Value Management, Project Management Institute (2019)
- GAO Cost Estimating and Assessment Guide (GAO-20-195G), U.S. Government Accountability Office (2020)
- NASA Earned Value Management (EVM) Implementation Handbook, NASA Office of the Chief Financial Officer (2023)
Keep going
Read the full guide: Earned Value Management Guide.
- Earned Value Management
- CPI / SPI Calculator
- Sensitivity Analysis
- What-If Analysis
- Project Completion Percentage Calculator
- Planned Value Calculator
Terms: To-complete performance index (TCPI).
More in this discipline: Performance & Forecasting.
Last reviewed October 2026. The arithmetic is covered by unit tests. See our methodology or report an error.