Planned Value Calculator
Calculate the budgeted value of work scheduled by the status date for earned value analysis.
- Use this when
- Use this at a regular status date after the scope, schedule, and cost baselines have been approved and progress can be measured objectively.
- Prepare
- Confirm the status date and bring consistent planned value, earned value, actual cost, and budget-at-completion data from the same reporting period.
- Decision supported
- Use the signal to decide whether to investigate variance, revise the forecast, protect contingency, or initiate corrective action.
Practitioner guidance and limitations
Interpret and act
Focus on trend and materiality, not a single isolated number. Pair indices and variances with milestone health, risk exposure, and the remaining work.
Professional caution
EVM is only as reliable as the baseline and progress-measurement method. Do not mix data from different cut-off dates or count effort as earned scope.
Learn the topic: concept, PMP lens, and common mistakes
Core concept
Earned Value Management integrates approved scope, schedule, and actual cost at one status date. Earned value represents budgeted value of completed scope—not effort consumed or invoices paid.
Professional application
Use trends in variance and efficiency indices to identify the cause, update the forecast, and agree corrective action while useful options still remain.
PMP exam and practice lens
Remember the direction of the core measures: positive CV and SV are favorable; CPI and SPI above 1.00 are favorable. Select the EAC or TCPI formula that matches the scenario assumptions.
Common mistakes
- Mixing PV, EV, and AC from different reporting cut-off dates
- Claiming progress without objective completion rules
- Treating an index as the explanation instead of investigating root cause
Before you trust the result
- Confirm one status date and consistent units.
- Retain the input source, owner, and confidence.
- Sense-check the result against an independent benchmark.
- Record the decision, action owner, and review date.
Related practice tools
How the Planned Value calculation works
Calculate the budgeted value of work scheduled by the status date for earned value analysis.
Formulas
| Measure | Formula |
|---|---|
| Planned Value (PV) | Planned Value (PV) = Budget at Completion × planned completion percentage |
What the terms mean
- Budget at Completion
- Currency amount
- Planned completion by status date
- Measured in %
Worked example
Inputs
- Budget at Completion = $900,000
- Planned completion by status date = 45 %
Results
- Planned Value = $405,000
- Planned completion = 45.0%
- Budget scheduled after status date = $495,000
What it means: Use the approved time-phased performance measurement baseline and one consistent status date; PV is not actual spending or completed work.
Frequently asked questions
What does the Planned Value calculator do?
Calculate the budgeted value of work scheduled by the status date for earned value analysis.
What is the formula for planned value?
Planned Value (PV) = Budget at Completion × planned completion percentage.
What inputs do I need?
You need: budget at completion, planned completion by status date. Use figures from the same status date and the same units.
How do I read the result?
Use the approved time-phased performance measurement baseline and one consistent status date; PV is not actual spending or completed work. Treat the figure as one piece of evidence and compare it with your baseline, thresholds and project context.
Sources and method
This calculator applies the formula shown above to the figures you enter. The worked example is computed by the same code.
Keep going
Read the full guide: Earned Value Management Guide.
- Earned Value Management
- CPI / SPI Calculator
- TCPI Calculator
- Sensitivity Analysis
- What-If Analysis
- Project Completion Percentage Calculator
Terms: Planned value (PV).
More in this discipline: Performance & Forecasting.
Last reviewed October 2026. See our methodology or report an error.