PMP formulas cheat sheet, with worked examples

Every formula a project manager or PMP candidate needs, grouped by topic. Each row links to a calculator so you can check your own working. Figures in the example column are computed by the same tested code as the calculators.

Earned value management

Example inputs: PV $50,000, EV $45,000, AC $55,000, BAC $200,000.

MeasureFormulaExampleCalculator
Cost variance (CV)EV − AC−$10,000Open
Schedule variance (SV)EV − PV−$5,000Open
Cost performance index (CPI)EV ÷ AC0.82Open
Schedule performance index (SPI)EV ÷ PV0.90Open
EAC, cost trend continuesBAC ÷ CPI$244,444Open
EAC, one-off varianceAC + (BAC − EV)$210,000Open
EAC, cost and schedule drive costAC + (BAC − EV) ÷ (CPI × SPI)$265,494Open
EAC, new estimateAC + bottom-up ETCdepends on ETCOpen
Estimate to complete (ETC)EAC − AC$189,444Open
Variance at completion (VAC)BAC − EAC−$44,444Open
TCPI (to meet BAC)(BAC − EV) ÷ (BAC − AC)1.07Open
TCPI (to meet EAC)(BAC − EV) ÷ (EAC − AC)uses your EACOpen

Schedule and estimating

Example: O = 8, M = 12, P = 20 days.

MeasureFormulaExampleCalculator
PERT expected duration(O + 4M + P) ÷ 612.67 daysOpen
PERT standard deviation(P − O) ÷ 62.00 daysOpen
Triangular expected duration(O + M + P) ÷ 313.33 daysOpen
Variance((P − O) ÷ 6)²4.00Open
Early finish (EF)ES + durationOpen
Late start (LS)LF − durationOpen
Total floatLS − ES or LF − EFOpen
Free floatEarliest successor ES − EFOpen

Risk and communication

MeasureFormulaExampleCalculator
Expected monetary value (EMV)Probability × impact30% × −$50,000 = −$15,000Open
Risk scoreProbability × impact4 × 4 = 16Open
Communication channelsn(n − 1) ÷ 210 people = 45Open

Finance

Example: invest $100,000; receive $25,000, $30,000, $35,000, $40,000, $45,000 in years 1 to 5; 10% discount rate.

MeasureFormulaExampleCalculator
Present value (PV)FV ÷ (1 + r)ⁿ$45,000 in year 5 = $27,941Open
Net present value (NPV)Σ CFₜ ÷ (1 + r)ᵗ$29,079Open
Return on investment (ROI)(benefit − cost) ÷ cost × 100($175,000 − $100,000) ÷ $100,000 = 75%Open
Payback periodYears before recovery + unrecovered ÷ next-year flow3.25 yearsOpen
Benefit-cost ratio (BCR)PV of benefits ÷ PV of costsOpen
Break-even unitsFixed costs ÷ (price − variable cost)$10,000 ÷ ($50 − $30) = 500Open
Point of total assumption(ceiling − target price) ÷ buyer’s share ratio + target costOpen

Quality and statistics

MeasureFormulaExampleCalculator
Defect densityDefects ÷ sizeOpen
Cp(USL − LSL) ÷ 6σOpen
Cpkmin[(USL − μ) ÷ 3σ, (μ − LSL) ÷ 3σ]Open
DPMODefects ÷ (units × opportunities) × 1,000,000Open
Normal ranges±1σ = 68.27%, ±2σ = 95.45%, ±3σ = 99.73%Open

Agile and flow

MeasureFormulaExampleCalculator
Sprints neededRemaining backlog ÷ velocity210 ÷ 42 = 5Open
Little’s LawAverage WIP = throughput × average cycle time5 per week × 3 weeks = 15Open
Cycle timeFinish date − start dateOpen
Lead timeWait + cycle + deploymentOpen

How to remember the earned value formulas

  • EV is always first in the variances and indices: CV = EV − AC, SV = EV − PV, CPI = EV ÷ AC, SPI = EV ÷ PV.
  • Variances are differences (money); indices are ratios (no units).
  • Above zero or above 1.0 is good for all four.
  • EAC always starts from AC or BAC; pick the formula by what you expect the rest of the work to cost.

Related

Sources for the earned value material: The Standard for Earned Value Management (PMI). PMP is a registered mark of the Project Management Institute, Inc. ProjectCalc is not affiliated with PMI.