Cheat sheet
PMP formulas cheat sheet, with worked examples
Every formula a project manager or PMP candidate needs, grouped by topic. Each row links to a calculator so you can check your own working. Figures in the example column are computed by the same tested code as the calculators.
Earned value management
Example inputs: PV $50,000, EV $45,000, AC $55,000, BAC $200,000.
| Measure | Formula | Example | Calculator |
|---|---|---|---|
| Cost variance (CV) | EV − AC | −$10,000 | Open |
| Schedule variance (SV) | EV − PV | −$5,000 | Open |
| Cost performance index (CPI) | EV ÷ AC | 0.82 | Open |
| Schedule performance index (SPI) | EV ÷ PV | 0.90 | Open |
| EAC, cost trend continues | BAC ÷ CPI | $244,444 | Open |
| EAC, one-off variance | AC + (BAC − EV) | $210,000 | Open |
| EAC, cost and schedule drive cost | AC + (BAC − EV) ÷ (CPI × SPI) | $265,494 | Open |
| EAC, new estimate | AC + bottom-up ETC | depends on ETC | Open |
| Estimate to complete (ETC) | EAC − AC | $189,444 | Open |
| Variance at completion (VAC) | BAC − EAC | −$44,444 | Open |
| TCPI (to meet BAC) | (BAC − EV) ÷ (BAC − AC) | 1.07 | Open |
| TCPI (to meet EAC) | (BAC − EV) ÷ (EAC − AC) | uses your EAC | Open |
Schedule and estimating
Example: O = 8, M = 12, P = 20 days.
| Measure | Formula | Example | Calculator |
|---|---|---|---|
| PERT expected duration | (O + 4M + P) ÷ 6 | 12.67 days | Open |
| PERT standard deviation | (P − O) ÷ 6 | 2.00 days | Open |
| Triangular expected duration | (O + M + P) ÷ 3 | 13.33 days | Open |
| Variance | ((P − O) ÷ 6)² | 4.00 | Open |
| Early finish (EF) | ES + duration | Open | |
| Late start (LS) | LF − duration | Open | |
| Total float | LS − ES or LF − EF | Open | |
| Free float | Earliest successor ES − EF | Open |
Risk and communication
Finance
Example: invest $100,000; receive $25,000, $30,000, $35,000, $40,000, $45,000 in years 1 to 5; 10% discount rate.
| Measure | Formula | Example | Calculator |
|---|---|---|---|
| Present value (PV) | FV ÷ (1 + r)ⁿ | $45,000 in year 5 = $27,941 | Open |
| Net present value (NPV) | Σ CFₜ ÷ (1 + r)ᵗ | $29,079 | Open |
| Return on investment (ROI) | (benefit − cost) ÷ cost × 100 | ($175,000 − $100,000) ÷ $100,000 = 75% | Open |
| Payback period | Years before recovery + unrecovered ÷ next-year flow | 3.25 years | Open |
| Benefit-cost ratio (BCR) | PV of benefits ÷ PV of costs | Open | |
| Break-even units | Fixed costs ÷ (price − variable cost) | $10,000 ÷ ($50 − $30) = 500 | Open |
| Point of total assumption | (ceiling − target price) ÷ buyer’s share ratio + target cost | Open |
Quality and statistics
Agile and flow
How to remember the earned value formulas
- EV is always first in the variances and indices: CV = EV − AC, SV = EV − PV, CPI = EV ÷ AC, SPI = EV ÷ PV.
- Variances are differences (money); indices are ratios (no units).
- Above zero or above 1.0 is good for all four.
- EAC always starts from AC or BAC; pick the formula by what you expect the rest of the work to cost.
Related
- Earned value management guide
- PMP scenario question strategy
- Glossary of project management terms
- Comparisons: CPI vs SPI, NPV vs IRR and more
Sources for the earned value material: The Standard for Earned Value Management (PMI). PMP is a registered mark of the Project Management Institute, Inc. ProjectCalc is not affiliated with PMI.