Estimate to Complete Calculator

Estimate the remaining cost required to complete project work using the current forecast and cost-efficiency evidence.

Runs in your browserProfessional PM contextAssumptions remain visible

Inputs

Calculation data

Use this when
Use this at a regular status date after the scope, schedule, and cost baselines have been approved and progress can be measured objectively.
Prepare
Confirm the status date and bring consistent planned value, earned value, actual cost, and budget-at-completion data from the same reporting period.
Decision supported
Use the signal to decide whether to investigate variance, revise the forecast, protect contingency, or initiate corrective action.
Practitioner guidance and limitations

Interpret and act

Focus on trend and materiality, not a single isolated number. Pair indices and variances with milestone health, risk exposure, and the remaining work.

Professional caution

EVM is only as reliable as the baseline and progress-measurement method. Do not mix data from different cut-off dates or count effort as earned scope.

Learn the topic: concept, PMP lens, and common mistakes

Core concept

Earned Value Management integrates approved scope, schedule, and actual cost at one status date. Earned value represents budgeted value of completed scope—not effort consumed or invoices paid.

Professional application

Use trends in variance and efficiency indices to identify the cause, update the forecast, and agree corrective action while useful options still remain.

PMP exam and practice lens

Remember the direction of the core measures: positive CV and SV are favorable; CPI and SPI above 1.00 are favorable. Select the EAC or TCPI formula that matches the scenario assumptions.

Common mistakes

  • Mixing PV, EV, and AC from different reporting cut-off dates
  • Claiming progress without objective completion rules
  • Treating an index as the explanation instead of investigating root cause

Before you trust the result

  • Confirm one status date and consistent units.
  • Retain the input source, owner, and confidence.
  • Sense-check the result against an independent benchmark.
  • Record the decision, action owner, and review date.

How the Estimate to Complete calculation works

Estimate the remaining cost required to complete project work using the current forecast and cost-efficiency evidence.

Formulas

MeasureFormula
ETC from forecastETC from forecast = EAC − AC
ETC from performanceETC from performance = (BAC − EV) ÷ CPI

What the terms mean

Budget at Completion
Currency amount
Earned Value
Currency amount
Actual Cost
Currency amount
Approved current EAC
Currency amount

Worked example

Inputs

  • Budget at Completion = $800,000
  • Earned Value = $360,000
  • Actual Cost = $420,000
  • Approved current EAC = $920,000

Results

  1. ETC from current EAC = $500,000
  2. ETC if CPI continues = $513,333
  3. Current CPI = 0.86 index

What it means: Reconcile the two ETC views and document whether remaining work is expected to follow current efficiency or a bottom-up recovery forecast.

Frequently asked questions

What does the Estimate to Complete calculator do?

Estimate the remaining cost required to complete project work using the current forecast and cost-efficiency evidence.

What is the formula for estimate to complete?

ETC from forecast = EAC − AC; ETC from performance = (BAC − EV) ÷ CPI.

What inputs do I need?

You need: budget at completion, earned value, actual cost, approved current eac. Use figures from the same status date and the same units.

How do I read the result?

Reconcile the two ETC views and document whether remaining work is expected to follow current efficiency or a bottom-up recovery forecast. Treat the figure as one piece of evidence and compare it with your baseline, thresholds and project context.

Sources and method

This calculator applies the formula shown above to the figures you enter. The worked example is computed by the same code.

Keep going

Read the full guide: Earned Value Management Guide.

Terms: Estimate at completion (EAC), Estimate to complete (ETC).

More in this discipline: Performance & Forecasting.