Estimate to complete (ETC)
Estimate to complete is the forecast cost still needed to finish the work.
Formula
ETC = EAC − AC
Worked example
With EAC $244,444 and AC $55,000, ETC = $189,444.
Why it matters
ETC is the amount you still need to fund.
Common mistake
Treating ETC as the remaining budget. Remaining budget is BAC − AC.
Try it in a calculator
- Estimate to Complete Calculator: Estimate the remaining cost required to complete project work using the current forecast and cost-efficiency evidence.
- Estimate at Completion: Forecast final project cost from current performance.
Frequently asked questions
Is ETC the same as remaining budget?
No. ETC is a forecast of what is still needed; remaining budget is what is left of the approved amount.
Can ETC be estimated bottom-up?
Yes. Re-estimate the remaining work and use EAC = AC + that ETC.