Estimate to complete (ETC)

Estimate to complete is the forecast cost still needed to finish the work.

Formula

ETC = EAC − AC

Worked example

With EAC $244,444 and AC $55,000, ETC = $189,444.

Why it matters

ETC is the amount you still need to fund.

Common mistake

Treating ETC as the remaining budget. Remaining budget is BAC − AC.

Try it in a calculator

Frequently asked questions

Is ETC the same as remaining budget?

No. ETC is a forecast of what is still needed; remaining budget is what is left of the approved amount.

Can ETC be estimated bottom-up?

Yes. Re-estimate the remaining work and use EAC = AC + that ETC.