Budget at completion (BAC)

Budget at completion is the total approved budget for the work, the reference for all cost forecasts.

Formula

BAC = sum of all work package budgets (the cost baseline)

Worked example

A project with $840,000 of work package budgets and contingency has a BAC of $840,000. Management reserve of $37,500 is held outside it.

Why it matters

Forecasts such as EAC and VAC are measured against BAC.

Common mistake

Including management reserve in BAC, which hides overruns from earned value reports.

Try it in a calculator

Frequently asked questions

Does BAC include contingency?

Yes. Contingency is inside the cost baseline. Management reserve is outside it.

Can BAC change?

Yes, through approved change control.