Budget at completion (BAC)
Budget at completion is the total approved budget for the work, the reference for all cost forecasts.
Formula
BAC = sum of all work package budgets (the cost baseline)
Worked example
A project with $840,000 of work package budgets and contingency has a BAC of $840,000. Management reserve of $37,500 is held outside it.
Why it matters
Forecasts such as EAC and VAC are measured against BAC.
Common mistake
Including management reserve in BAC, which hides overruns from earned value reports.
Try it in a calculator
- Budget at Completion: Develop and review the approved total project budget.
- Estimate at Completion: Forecast final project cost from current performance.
Frequently asked questions
Does BAC include contingency?
Yes. Contingency is inside the cost baseline. Management reserve is outside it.
Can BAC change?
Yes, through approved change control.