Cost performance index (CPI)
CPI is earned value divided by actual cost. A value below 1.0 means the project is over budget for the work done.
Formula
CPI = EV ÷ AC
Worked example
PV $50,000, EV $45,000, AC $55,000, BAC $200,000: CPI = 45,000 ÷ 55,000 = 0.82. Each dollar spent has earned about 82 cents of planned value.
Why it matters
CPI shows cost efficiency to date and is the basis of the most common forecast, EAC = BAC ÷ CPI.
Common mistake
Reading one period’s CPI as a trend. Compare cumulative and period values.
Try it in a calculator
- CPI / SPI Calculator: Measure cost and schedule efficiency.
- Earned Value Management: Integrate scope, schedule, and cost performance.
Frequently asked questions
What is a good CPI?
1.0 or above is on or under budget. Many organisations act below about 0.9, but set your own threshold.
Can CPI be above 1 and the project still be late?
Yes. CPI measures cost efficiency only; SPI measures schedule progress.