Cost performance index (CPI)

CPI is earned value divided by actual cost. A value below 1.0 means the project is over budget for the work done.

Formula

CPI = EV ÷ AC

Worked example

PV $50,000, EV $45,000, AC $55,000, BAC $200,000: CPI = 45,000 ÷ 55,000 = 0.82. Each dollar spent has earned about 82 cents of planned value.

Why it matters

CPI shows cost efficiency to date and is the basis of the most common forecast, EAC = BAC ÷ CPI.

Common mistake

Reading one period’s CPI as a trend. Compare cumulative and period values.

Try it in a calculator

Frequently asked questions

What is a good CPI?

1.0 or above is on or under budget. Many organisations act below about 0.9, but set your own threshold.

Can CPI be above 1 and the project still be late?

Yes. CPI measures cost efficiency only; SPI measures schedule progress.