Schedule performance index (SPI)
SPI is earned value divided by planned value. A value below 1.0 means less work is done than planned.
Formula
SPI = EV ÷ PV
Worked example
PV $50,000, EV $45,000, AC $55,000, BAC $200,000: SPI = 45,000 ÷ 50,000 = 0.90. Ninety percent of the planned work is done.
Why it matters
SPI shows schedule progress in money terms and flags a slip early.
Common mistake
Using SPI late in a project. It drifts to 1.0 as work finishes, so use the critical path or earned schedule instead.
Try it in a calculator
- CPI / SPI Calculator: Measure cost and schedule efficiency.
- Schedule Variance: Compare earned value with planned value.
Frequently asked questions
Is an SPI of 0.9 bad?
It means about 10% of planned work is not yet done. Whether that matters depends on whether the late work is on the critical path.
Is SPI measured in time?
No. It is a ratio of money. Earned schedule converts it to time.