Schedule performance index (SPI)

SPI is earned value divided by planned value. A value below 1.0 means less work is done than planned.

Formula

SPI = EV ÷ PV

Worked example

PV $50,000, EV $45,000, AC $55,000, BAC $200,000: SPI = 45,000 ÷ 50,000 = 0.90. Ninety percent of the planned work is done.

Why it matters

SPI shows schedule progress in money terms and flags a slip early.

Common mistake

Using SPI late in a project. It drifts to 1.0 as work finishes, so use the critical path or earned schedule instead.

Try it in a calculator

Frequently asked questions

Is an SPI of 0.9 bad?

It means about 10% of planned work is not yet done. Whether that matters depends on whether the late work is on the critical path.

Is SPI measured in time?

No. It is a ratio of money. Earned schedule converts it to time.

Learn more