Cost variance (CV)
Cost variance is earned value minus actual cost. A negative value means the completed work cost more than budgeted.
Formula
CV = EV − AC
Worked example
PV $50,000, EV $45,000, AC $55,000, BAC $200,000: CV = 45,000 − 55,000 = −$10,000, an overrun on the work done.
Why it matters
CV gives the size of the overrun in money.
Common mistake
Comparing AC with the total budget instead of with EV.
Try it in a calculator
- Cost Variance: Compare earned value with actual cost.
- Earned Value Management: Integrate scope, schedule, and cost performance.
Frequently asked questions
What does a negative CV mean?
Over budget for the work completed.
How is CV percent calculated?
CV ÷ EV × 100.