Cost variance (CV)

Cost variance is earned value minus actual cost. A negative value means the completed work cost more than budgeted.

Formula

CV = EV − AC

Worked example

PV $50,000, EV $45,000, AC $55,000, BAC $200,000: CV = 45,000 − 55,000 = −$10,000, an overrun on the work done.

Why it matters

CV gives the size of the overrun in money.

Common mistake

Comparing AC with the total budget instead of with EV.

Try it in a calculator

Frequently asked questions

What does a negative CV mean?

Over budget for the work completed.

How is CV percent calculated?

CV ÷ EV × 100.