Skip to content

Earned value (EV)

Earned value is the budgeted cost of the work actually completed at a status date. It measures progress in money, not effort spent.

Formula

EV = % complete × BAC (or the sum of budgets of finished work packages)

Worked example

A $10,000 work package that is 50% complete by an agreed rule has an EV of $5,000, whatever it has cost so far.

Why it matters

EV is the anchor for every earned value measure. CV, SV, CPI, SPI and the forecasts are all built from it.

Common mistake

Counting hours worked or money invoiced as earned value.

Try it in a calculator

Frequently asked questions

Is earned value the same as actual cost?

No. Earned value is what the completed work was budgeted to cost. Actual cost is what it really cost.

How is progress measured for EV?

Agree a rule before work starts, such as 0/100, 50/50, milestones or units complete, and apply it consistently.

Learn more