Actual cost (AC)

Actual cost is what the completed work has really cost up to a status date, including costs incurred but not yet paid.

Formula

AC = total cost incurred for work performed

Worked example

If the work completed by month 3 has cost $55,000 including accrued invoices, AC is $55,000.

Why it matters

AC is compared with EV to show cost efficiency.

Common mistake

Using only cash paid, which leaves out accruals and understates AC.

Try it in a calculator

Frequently asked questions

What is the old name for actual cost?

Actual cost of work performed (ACWP).

Should AC include overhead?

Include whatever the baseline budget includes, so the comparison is like for like.