Actual cost (AC)
Actual cost is what the completed work has really cost up to a status date, including costs incurred but not yet paid.
Formula
AC = total cost incurred for work performed
Worked example
If the work completed by month 3 has cost $55,000 including accrued invoices, AC is $55,000.
Why it matters
AC is compared with EV to show cost efficiency.
Common mistake
Using only cash paid, which leaves out accruals and understates AC.
Try it in a calculator
- Earned Value Management: Integrate scope, schedule, and cost performance.
- Cost Variance: Compare earned value with actual cost.
Frequently asked questions
What is the old name for actual cost?
Actual cost of work performed (ACWP).
Should AC include overhead?
Include whatever the baseline budget includes, so the comparison is like for like.