Planned value (PV)

Planned value is the approved budget for the work scheduled to be completed by a status date.

Formula

PV = budgeted cost of work scheduled

Worked example

If the plan says $50,000 of work should be done by the end of month 3, PV at that date is $50,000.

Why it matters

PV is the baseline against which schedule performance is measured.

Common mistake

Using PV from a different status date than EV and AC.

Try it in a calculator

Frequently asked questions

What is the old name for planned value?

Budgeted cost of work scheduled (BCWS).

Does PV change during the project?

Only if the baseline is formally changed.