Planned value (PV)
Planned value is the approved budget for the work scheduled to be completed by a status date.
Formula
PV = budgeted cost of work scheduled
Worked example
If the plan says $50,000 of work should be done by the end of month 3, PV at that date is $50,000.
Why it matters
PV is the baseline against which schedule performance is measured.
Common mistake
Using PV from a different status date than EV and AC.
Try it in a calculator
- Planned Value Calculator: Calculate the budgeted value of work scheduled by the status date for earned value analysis.
- Schedule Variance: Compare earned value with planned value.
Frequently asked questions
What is the old name for planned value?
Budgeted cost of work scheduled (BCWS).
Does PV change during the project?
Only if the baseline is formally changed.