Estimate at completion (EAC)

Estimate at completion is the forecast of total project cost: what has been spent plus what is expected to be spent.

Formula

EAC = BAC ÷ CPI (typical). Others: AC + (BAC − EV); AC + (BAC − EV) ÷ (CPI × SPI); AC + bottom-up ETC

Worked example

PV $50,000, EV $45,000, AC $55,000, BAC $200,000: EAC = 200,000 ÷ 0.8182 = $244,444 if the cost trend continues, or $210,000 if the overrun was a one-off.

Why it matters

EAC tells the sponsor where the project will end up if nothing changes.

Common mistake

Quoting one EAC without saying which formula it uses.

Try it in a calculator

Frequently asked questions

Which EAC formula should I use?

Choose by what you expect: BAC ÷ CPI if the trend continues, AC + (BAC − EV) if it was a one-off.

What is the difference between EAC and ETC?

EAC is the total forecast; ETC is the part still to come: EAC − AC.