To-complete performance index (TCPI)
TCPI is the cost efficiency the project must achieve on the remaining work to meet a target such as BAC or EAC.
Formula
TCPI = (BAC − EV) ÷ (BAC − AC)
Worked example
PV $50,000, EV $45,000, AC $55,000, BAC $200,000: TCPI = 155,000 ÷ 145,000 = 1.07, about 30% better than the CPI of 0.82 achieved so far.
Why it matters
TCPI shows whether the original budget is still realistic.
Common mistake
Targeting BAC after the budget is already spent: TCPI is then undefined or negative.
Try it in a calculator
- TCPI Calculator: Calculate the efficiency needed to meet a cost target.
- Estimate at Completion: Forecast final project cost from current performance.
Frequently asked questions
What is a good TCPI?
Close to 1.0 is good. Well above your CPI means the target is unlikely without change.
When use TCPI to EAC?
When BAC is out of reach and a revised EAC is the target.