Skip to content

To-complete performance index (TCPI)

TCPI is the cost efficiency the project must achieve on the remaining work to meet a target such as BAC or EAC.

Formula

TCPI = (BAC − EV) ÷ (BAC − AC)

Worked example

PV $50,000, EV $45,000, AC $55,000, BAC $200,000: TCPI = 155,000 ÷ 145,000 = 1.07, about 30% better than the CPI of 0.82 achieved so far.

Why it matters

TCPI shows whether the original budget is still realistic.

Common mistake

Targeting BAC after the budget is already spent: TCPI is then undefined or negative.

Try it in a calculator

Frequently asked questions

What is a good TCPI?

Close to 1.0 is good. Well above your CPI means the target is unlikely without change.

When use TCPI to EAC?

When BAC is out of reach and a revised EAC is the target.

Learn more