Project Budget Overrun Percentage Calculator

Calculate the amount and percentage by which actual or forecast project cost exceeds the approved budget.

Runs in your browserProfessional PM contextAssumptions remain visible

Inputs

Calculation data

Use this when
Use this during business-case development, project selection, or a stage-gate review when financial value must be compared on a consistent basis.
Prepare
Use approved cash-flow estimates, timing assumptions, the relevant discount or hurdle rate, and a clearly defined analysis period.
Decision supported
The result helps support go/no-go, sequencing, funding, or option-selection decisions. Compare alternatives using the same assumptions.
Practitioner guidance and limitations

Interpret and act

Read the result alongside strategic fit, risk, capacity, and mandatory obligations. A strong financial metric does not make an option executable by itself.

Professional caution

Small changes in benefits, timing, or discount rate can change the conclusion. Record the source, owner, and date of every material assumption.

Learn the topic: concept, PMP lens, and common mistakes

Core concept

Financial metrics translate expected project costs and benefits into comparable evidence. They are most useful when alternatives use the same valuation date, time horizon, currency, and treatment of risk.

Professional application

Use the result to strengthen a business case or option recommendation, then test the conclusion with conservative, expected, and optimistic assumptions.

PMP exam and practice lens

For PMP-style questions, distinguish project selection measures from cost-control measures. ROI is simple but ignores timing; NPV reflects the time value of money; IRR is a rate; payback emphasizes recovery speed.

Common mistakes

  • Comparing options with different time horizons or cost boundaries
  • Counting benefits without an accountable owner or realization date
  • Presenting a single-point forecast without sensitivity analysis

Before you trust the result

  • Confirm one status date and consistent units.
  • Retain the input source, owner, and confidence.
  • Sense-check the result against an independent benchmark.
  • Record the decision, action owner, and review date.

How the Project Budget Overrun Percentage calculation works

Calculate the amount and percentage by which actual or forecast project cost exceeds the approved budget.

Formulas

MeasureFormula
Budget overrun %Budget overrun % = (Actual or forecast cost − approved budget) ÷ approved budget × 100

What the terms mean

Approved project budget
Currency amount
Actual or forecast cost
Currency amount

Worked example

Inputs

  • Approved project budget = $500,000
  • Actual or forecast cost = $565,000

Results

  1. Budget variance = $65,000
  2. Budget overrun percentage = 13.0%

What it means: The project is above its approved budget; separate root cause, approved change, risk draw, and performance effects before recommending action.

Frequently asked questions

What does the Project Budget Overrun Percentage calculator do?

Calculate the amount and percentage by which actual or forecast project cost exceeds the approved budget.

What is the formula for project budget overrun percentage?

Budget overrun % = (Actual or forecast cost − approved budget) ÷ approved budget × 100.

What inputs do I need?

You need: approved project budget, actual or forecast cost. Use figures from the same status date and the same units.

How do I read the result?

The project is above its approved budget; separate root cause, approved change, risk draw, and performance effects before recommending action. Treat the figure as one piece of evidence and compare it with your baseline, thresholds and project context.

Sources and method

This calculator applies the formula shown above to the figures you enter. The worked example is computed by the same code.

Keep going

Read the full guide: Project Financial Analysis Guide.

More in this discipline: Cost & Financial Analysis.

Last reviewed October 2026. See our methodology or report an error.