Contractor vs FTE Cost Calculator
Compare annual contractor cost with fully loaded employee cost for a project role or capability decision.
- Use this when
- Use this during resource planning, team formation, sprint or phase planning, and whenever demand appears to exceed available capacity.
- Prepare
- Separate gross availability from productive capacity and include calendars, leave, skills, allocation limits, overhead, and realistic focus factors.
- Decision supported
- Use the output to rebalance assignments, change timing, secure skills, adjust scope, or discuss sustainable delivery options with sponsors.
Practitioner guidance and limitations
Interpret and act
Treat high utilization cautiously: a system operating near full capacity often creates queues, delays, quality issues, and burnout.
Professional caution
People are not interchangeable units. Validate skill fit, onboarding, collaboration overhead, and individual constraints before changing the plan.
Learn the topic: concept, PMP lens, and common mistakes
Core concept
Resource capacity is net productive availability after calendars, leave, operational work, collaboration, and focus loss. Headcount alone is not a capacity measure.
Professional application
Use the result to resolve overload through sequencing, leveling, skill changes, scope trade-offs, or additional capacity—not sustained over-utilization.
PMP exam and practice lens
Resource leveling may change the critical path and finish date; resource smoothing works within available float. A RACI chart clarifies accountability but does not solve insufficient capacity.
Common mistakes
- Planning against gross hours instead of net availability
- Treating people with different skills as interchangeable
- Targeting 100% utilization and creating queues, burnout, and quality loss
Before you trust the result
- Confirm one status date and consistent units.
- Retain the input source, owner, and confidence.
- Sense-check the result against an independent benchmark.
- Record the decision, action owner, and review date.
Related practice tools
How the Contractor vs FTE Cost calculation works
Compare annual contractor cost with fully loaded employee cost for a project role or capability decision.
Formulas
| Measure | Formula |
|---|---|
| Loaded FTE cost | Loaded FTE cost = Salary × (1 + benefits % + overhead %) |
| Contractor cost | Contractor cost = Hourly rate × annual hours |
What the terms mean
- Annual FTE salary
- Currency amount
- Benefits load
- Measured in %
- Employer overhead
- Measured in %
- Contractor hourly rate
- Currency amount
- Annual contractor hours
- Measured in hours
Worked example
Inputs
- Annual FTE salary = $110,000
- Benefits load = 28 %
- Employer overhead = 18 %
- Contractor hourly rate = $95
- Annual contractor hours = 1,800 hours
Results
- Fully loaded FTE cost = $160,600 / year
- Contractor cost = $171,000 / year
- Contractor premium = $10,400
What it means: The contractor has a direct cost premium; weigh speed, flexibility, scarcity, duration, employment rules, knowledge retention, and transition risk.
Frequently asked questions
What does the Contractor vs FTE Cost calculator do?
Compare annual contractor cost with fully loaded employee cost for a project role or capability decision.
What is the formula for contractor vs fte cost?
Loaded FTE cost = Salary × (1 + benefits % + overhead %); Contractor cost = Hourly rate × annual hours.
What inputs do I need?
You need: annual fte salary, benefits load, employer overhead, contractor hourly rate, annual contractor hours. Use figures from the same status date and the same units.
How do I read the result?
The contractor has a direct cost premium; weigh speed, flexibility, scarcity, duration, employment rules, knowledge retention, and transition risk. Treat the figure as one piece of evidence and compare it with your baseline, thresholds and project context.
Sources and method
This calculator applies the formula shown above to the figures you enter. The worked example is computed by the same code.
Keep going
Read the full guide: Project Procurement and Contract Management Guide.
- Resource Utilization
- Resource Cost
- Resource Leveling
- Man-Hours Calculator
- Workload Planner
- Team Productivity
More in this discipline: Resources & Teams.
Last reviewed October 2026. See our methodology or report an error.