Scope creep
Scope creep is uncontrolled growth in project scope without matching changes to cost, time and resources.
Formula
Duration impact = days added ÷ original duration × 100
Worked example
18 days added to a 120-day project is a 15% duration impact.
Why it matters
Small unmanaged changes add up to large overruns.
Common mistake
Confusing approved, controlled change with creep.
Try it in a calculator
- Scope Creep Risk: Assess conditions that make uncontrolled scope growth likely.
- Scope Change Rate Calculator: Track approved scope changes relative to the baseline requirement or work-package count during a reporting period.
Frequently asked questions
Is all scope change creep?
No. Approved, evaluated change is controlled change.
How is it prevented?
Through change control and a clear scope baseline.