Schedule Crash Cost per Day Calculator
Calculate the incremental cost per day saved when evaluating a critical-path activity for schedule crashing.
- Use this when
- Use this while developing or updating the schedule, testing a milestone commitment, or evaluating recovery from a forecast delay.
- Prepare
- Define activities at a manageable level, validate durations, calendars, dependencies, constraints, and—where relevant—optimistic and pessimistic estimates.
- Decision supported
- The output identifies where sequencing, reserves, resources, crashing, or fast-tracking may change the delivery date.
Practitioner guidance and limitations
Interpret and act
Protect critical and near-critical work, monitor path convergence, and treat available float as a shared project resource rather than spare time for one task owner.
Professional caution
A schedule model is not a commitment until resource availability, external dependencies, calendars, and risk responses have been validated with owners.
Learn the topic: concept, PMP lens, and common mistakes
Core concept
A credible schedule is a logic model of activities, dependencies, calendars, constraints, and uncertainty. Duration is an output of that model, not simply a requested date.
Professional application
Use the result to protect critical and near-critical work, challenge weak dependencies, and evaluate sequence or resource options before changing the commitment.
PMP exam and practice lens
Know the relationship between early/late dates, total float, and the critical path. PERT uses three-point estimates; crashing adds resources at added cost; fast-tracking overlaps work and increases risk.
Common mistakes
- Using mandatory date constraints to hide missing schedule logic
- Assuming all effort can run in parallel
- Consuming float locally without considering the integrated schedule
Before you trust the result
- Confirm one status date and consistent units.
- Retain the input source, owner, and confidence.
- Sense-check the result against an independent benchmark.
- Record the decision, action owner, and review date.
Related practice tools
How the Schedule Crash Cost per Day calculation works
Calculate the incremental cost per day saved when evaluating a critical-path activity for schedule crashing.
Formulas
| Measure | Formula |
|---|---|
| Crash cost per day | Crash cost per day = (Crash cost − normal cost) ÷ (Normal duration − crash duration) |
What the terms mean
- Normal activity cost
- Currency amount
- Crash activity cost
- Currency amount
- Normal duration
- Measured in days
- Crash duration
- Measured in days
Worked example
Inputs
- Normal activity cost = $48,000
- Crash activity cost = $66,000
- Normal duration = 20 days
- Crash duration = 14 days
Results
- Crash cost per day saved = $3,000 / day
- Maximum time saved = 6 days
- Incremental crash cost = $18,000
What it means: Compare critical-path crash candidates using cost per day saved, then validate resource feasibility, quality, risk, and whether the critical path changes.
Frequently asked questions
What does the Schedule Crash Cost per Day calculator do?
Calculate the incremental cost per day saved when evaluating a critical-path activity for schedule crashing.
What is the formula for schedule crash cost per day?
Crash cost per day = (Crash cost − normal cost) ÷ (Normal duration − crash duration).
What inputs do I need?
You need: normal activity cost, crash activity cost, normal duration, crash duration. Use figures from the same status date and the same units.
How do I read the result?
Compare critical-path crash candidates using cost per day saved, then validate resource feasibility, quality, risk, and whether the critical path changes. Treat the figure as one piece of evidence and compare it with your baseline, thresholds and project context.
Sources and method
This calculator applies the formula shown above to the figures you enter. The worked example is computed by the same code.
Keep going
Read the full guide: Project Schedule Management Guide.
- Critical Path Calculator
- PERT Calculator
- Float / Slack Analysis
- Schedule Compression
- Working Days
- Three-Point Estimate
Compare: Crashing vs Fast Tracking.
More in this discipline: Schedule & Estimating.