Crashing vs Fast Tracking
Crashing shortens a schedule by adding resources to critical activities, which costs money. Fast tracking shortens it by overlapping activities that were planned in sequence, which adds risk and rework. Use crashing when money is available and fast tracking when risk is acceptable.
Side by side
| Crashing | Fast tracking | |
|---|---|---|
| What changes | Resources on critical activities | Sequence: activities overlap |
| Main cost | Extra money | Extra risk and rework |
| Always works? | Only if the activity can be sped up | Only if activities can overlap |
| Applies to | Critical path activities | Critical path activities |
| Choose by | Lowest cost per day saved | Lowest added risk |
| Weakness | Diminishing returns | Rework if the first activity changes |
When to use each
- Use crashing when extra resources can really speed up the work and the cost per day is acceptable.
- Use fast tracking when dependencies are soft and the team can tolerate rework risk.
Example
Crashing an activity from 10 to 7 days for an extra $6,000 costs $2,000 per day saved. Compare that with the risk of starting the next activity early.
Common mistakes
- Compressing non-critical activities, which saves no time.
- Forgetting the critical path can switch after each change.
Frequently asked questions
Can both be used?
Yes, usually crashing the cheapest activities first and then fast tracking.
Do they change scope?
No. They compress the schedule without changing scope.