Crashing vs Fast Tracking

Crashing shortens a schedule by adding resources to critical activities, which costs money. Fast tracking shortens it by overlapping activities that were planned in sequence, which adds risk and rework. Use crashing when money is available and fast tracking when risk is acceptable.

Side by side

CrashingFast tracking
What changesResources on critical activitiesSequence: activities overlap
Main costExtra moneyExtra risk and rework
Always works?Only if the activity can be sped upOnly if activities can overlap
Applies toCritical path activitiesCritical path activities
Choose byLowest cost per day savedLowest added risk
WeaknessDiminishing returnsRework if the first activity changes

When to use each

  • Use crashing when extra resources can really speed up the work and the cost per day is acceptable.
  • Use fast tracking when dependencies are soft and the team can tolerate rework risk.

Example

Crashing an activity from 10 to 7 days for an extra $6,000 costs $2,000 per day saved. Compare that with the risk of starting the next activity early.

Common mistakes

  • Compressing non-critical activities, which saves no time.
  • Forgetting the critical path can switch after each change.

Frequently asked questions

Can both be used?

Yes, usually crashing the cheapest activities first and then fast tracking.

Do they change scope?

No. They compress the schedule without changing scope.