CPI vs SPI

CPI measures cost efficiency (earned value ÷ actual cost) and SPI measures schedule progress (earned value ÷ planned value). Both are ratios where 1.0 means on plan, so you need both to know whether a project is on budget and on time.

Side by side

CPISPI
FormulaEV ÷ ACEV ÷ PV
Compares earned value withActual costPlanned value
Question answeredAre we getting value for money?Are we making planned progress?
Below 1.0 meansOver budget for the work doneBehind the planned progress
Used to forecastEAC = BAC ÷ CPISchedule recovery effort
WeaknessSays nothing about timingDrifts to 1.0 as work finishes

When to use each

  • Use CPI when you want to judge cost performance or forecast the final cost.
  • Use SPI when you want to judge progress against the schedule baseline, early in the project.

Example

With PV $50,000, EV $45,000 and AC $55,000: CPI = 0.82 (over budget) and SPI = 0.90 (behind). Both are below 1.0, so the project is over budget and behind.

Common mistakes

  • Reading a good CPI as proof the project is on time.
  • Using SPI late in a project, when it always trends to 1.0.

Frequently asked questions

Can CPI be above 1 while SPI is below 1?

Yes. A project can be efficient but slow, for example if work is under-resourced.

Which matters more?

Neither on its own. A cost overrun and a delay need different responses.