CPI vs SPI
CPI measures cost efficiency (earned value ÷ actual cost) and SPI measures schedule progress (earned value ÷ planned value). Both are ratios where 1.0 means on plan, so you need both to know whether a project is on budget and on time.
Side by side
| CPI | SPI | |
|---|---|---|
| Formula | EV ÷ AC | EV ÷ PV |
| Compares earned value with | Actual cost | Planned value |
| Question answered | Are we getting value for money? | Are we making planned progress? |
| Below 1.0 means | Over budget for the work done | Behind the planned progress |
| Used to forecast | EAC = BAC ÷ CPI | Schedule recovery effort |
| Weakness | Says nothing about timing | Drifts to 1.0 as work finishes |
When to use each
- Use CPI when you want to judge cost performance or forecast the final cost.
- Use SPI when you want to judge progress against the schedule baseline, early in the project.
Example
With PV $50,000, EV $45,000 and AC $55,000: CPI = 0.82 (over budget) and SPI = 0.90 (behind). Both are below 1.0, so the project is over budget and behind.
Common mistakes
- Reading a good CPI as proof the project is on time.
- Using SPI late in a project, when it always trends to 1.0.
Frequently asked questions
Can CPI be above 1 while SPI is below 1?
Yes. A project can be efficient but slow, for example if work is under-resourced.
Which matters more?
Neither on its own. A cost overrun and a delay need different responses.