NPV vs IRR

NPV gives the value a project creates in money, today, at a chosen discount rate. IRR gives the project’s return as a percentage. Use NPV as the primary decision measure; use IRR to communicate the return and to compare with a hurdle rate.

Side by side

NPVIRR
ResultAn amount of moneyA percentage rate
Needs a discount rate?Yes, as an inputNo: it is the output
Accept whenNPV > 0IRR > hurdle rate
Handles unusual cash flowsYesCan give several answers or none
Reflects project sizeYesNo
Reinvestment assumptionAt the discount rateAt the IRR (often unrealistic)

When to use each

  • Use NPV when choosing between projects of different size or when cash flows change sign.
  • Use IRR when you need to express the return as a rate or check it against a required return.

Example

For an investment of $100,000 returning $25,000, $30,000, $35,000, $40,000 and $45,000 over five years, NPV at 10% is $29,079 and IRR is 19.71%. Both say accept.

Common mistakes

  • Ranking projects of different size by IRR alone.
  • Using IRR when cash flows change sign more than once.

Frequently asked questions

Do NPV and IRR ever disagree?

Yes, for mutually exclusive projects of different size or timing. Prefer NPV.

What is MIRR?

A modified IRR that uses a finance rate and a reinvestment rate to avoid the unrealistic reinvestment assumption.