PERT vs CPM

CPM finds the longest path through a network using one duration per activity. PERT uses three estimates per activity to describe uncertainty. Both find the critical path; PERT adds a measure of how likely the path is to finish on time.

Side by side

PERTCPM
Duration inputOne estimate per activityOptimistic, most likely, pessimistic
Handles uncertaintyNoYes, through variance
OriginIndustrial projects (DuPont, 1950s)US Navy Polaris programme (1950s)
OutputCritical path, floatExpected duration, standard deviation, probability
Best whenDurations are well knownDurations are uncertain
WeaknessTreats estimates as certainIgnores other near-critical paths

When to use each

  • Use CPM when activity durations are reliable and you need the critical path and float.
  • Use PERT when durations are uncertain and you want an expected duration and a range.

Example

An activity with O = 8, M = 12 and P = 20 days has a PERT duration of 12.67 days and σ of 2 days. CPM would use a single value such as 12.

Common mistakes

  • Applying PERT to one path and ignoring parallel paths.
  • Adding standard deviations instead of variances.

Frequently asked questions

Can I use both together?

Yes. Compute PERT durations, then run CPM on them.

Is Monte Carlo better?

It handles many paths at once, but needs the same three-point inputs.