PERT vs CPM
CPM finds the longest path through a network using one duration per activity. PERT uses three estimates per activity to describe uncertainty. Both find the critical path; PERT adds a measure of how likely the path is to finish on time.
Side by side
| PERT | CPM | |
|---|---|---|
| Duration input | One estimate per activity | Optimistic, most likely, pessimistic |
| Handles uncertainty | No | Yes, through variance |
| Origin | Industrial projects (DuPont, 1950s) | US Navy Polaris programme (1950s) |
| Output | Critical path, float | Expected duration, standard deviation, probability |
| Best when | Durations are well known | Durations are uncertain |
| Weakness | Treats estimates as certain | Ignores other near-critical paths |
When to use each
- Use CPM when activity durations are reliable and you need the critical path and float.
- Use PERT when durations are uncertain and you want an expected duration and a range.
Example
An activity with O = 8, M = 12 and P = 20 days has a PERT duration of 12.67 days and σ of 2 days. CPM would use a single value such as 12.
Common mistakes
- Applying PERT to one path and ignoring parallel paths.
- Adding standard deviations instead of variances.
Frequently asked questions
Can I use both together?
Yes. Compute PERT durations, then run CPM on them.
Is Monte Carlo better?
It handles many paths at once, but needs the same three-point inputs.