Cycle time
Cycle time is the elapsed time from starting work on an item to finishing it.
Formula
Cycle time = finish date − start date
Worked example
An item started on Monday and finished on Friday has a cycle time of 4 days.
Why it matters
The distribution of cycle times supports commitments such as “85% of items finish within 8 days”.
Common mistake
Quoting the average as a promise.
Try it in a calculator
- Cycle Time: Measure how long active work takes to finish.
- Throughput: Measure completed work per unit of time.
Frequently asked questions
Cycle time vs lead time?
Cycle time starts at work start; lead time at the request.
How do I shorten it?
Limit work in progress and remove blockers.