Velocity

Velocity is the amount of work, usually story points, a team completes per sprint. Teams use it to forecast how many sprints a backlog needs.

Formula

Sprints needed = remaining backlog ÷ average velocity

Worked example

Average velocity 42 points and a 210-point backlog gives 210 ÷ 42 = 5 sprints.

Why it matters

It turns history into a forecast.

Common mistake

Comparing velocity between teams, whose point scales differ.

Try it in a calculator

Frequently asked questions

Is velocity a Scrum requirement?

The Scrum Guide does not define it.

Count unfinished work?

No. Count only items that met the definition of done.