Velocity
Velocity is the amount of work, usually story points, a team completes per sprint. Teams use it to forecast how many sprints a backlog needs.
Formula
Sprints needed = remaining backlog ÷ average velocity
Worked example
Average velocity 42 points and a 210-point backlog gives 210 ÷ 42 = 5 sprints.
Why it matters
It turns history into a forecast.
Common mistake
Comparing velocity between teams, whose point scales differ.
Try it in a calculator
- Agile Velocity: Use completed work history for release forecasting.
- Agile Release Forecast Calculator: Estimate the number of sprints and calendar time required to complete a remaining backlog using demonstrated team velocity.
Frequently asked questions
Is velocity a Scrum requirement?
The Scrum Guide does not define it.
Count unfinished work?
No. Count only items that met the definition of done.