PERT (program evaluation and review technique)
PERT estimates an activity’s duration from three values (optimistic, most likely, pessimistic) and weights the most likely one four times.
Formula
E = (O + 4M + P) ÷ 6; σ = (P − O) ÷ 6
Worked example
O = 8, M = 12, P = 20 days: E = (8 + 48 + 20) ÷ 6 = 12.67 days and σ = 2 days.
Why it matters
PERT shows both the expected duration and how uncertain it is.
Common mistake
Adding standard deviations along a path. Add variances, then take the square root.
Try it in a calculator
- PERT Calculator: Create an uncertainty-aware duration estimate.
- Three-Point Estimate: Compare PERT and triangular estimates.
Frequently asked questions
What is the PERT formula?
(O + 4M + P) ÷ 6.
Why divide by 6?
The weights 1, 4 and 1 sum to 6.