PERT (program evaluation and review technique)

PERT estimates an activity’s duration from three values (optimistic, most likely, pessimistic) and weights the most likely one four times.

Formula

E = (O + 4M + P) ÷ 6; σ = (P − O) ÷ 6

Worked example

O = 8, M = 12, P = 20 days: E = (8 + 48 + 20) ÷ 6 = 12.67 days and σ = 2 days.

Why it matters

PERT shows both the expected duration and how uncertain it is.

Common mistake

Adding standard deviations along a path. Add variances, then take the square root.

Try it in a calculator

Frequently asked questions

What is the PERT formula?

(O + 4M + P) ÷ 6.

Why divide by 6?

The weights 1, 4 and 1 sum to 6.