Three-point estimate
A three-point estimate uses an optimistic, a most likely and a pessimistic value to describe an activity’s cost or duration.
Formula
Triangular: (O + M + P) ÷ 3. Beta (PERT): (O + 4M + P) ÷ 6
Worked example
O = 8, M = 12, P = 20: triangular mean 13.33, PERT mean 12.67.
Why it matters
A range invites a conversation about risk that a single number hides.
Common mistake
Using a pessimistic value that is not truly pessimistic, which understates risk.
Try it in a calculator
- Three-Point Estimate: Compare PERT and triangular estimates.
- PERT Calculator: Create an uncertainty-aware duration estimate.
Frequently asked questions
Beta or triangular?
Beta weights the most likely value more; triangular treats the three equally. Use the one your organisation specifies.
How many estimates are needed?
Three per activity.