Benefit-cost ratio (BCR)

The benefit-cost ratio divides the present value of benefits by the present value of costs. Above 1.0 means benefits outweigh costs.

Formula

BCR = PV of benefits ÷ PV of costs

Worked example

PV of benefits $136,162 and PV of costs $127,232 give a BCR of 1.07.

Why it matters

BCR is common in public-sector and capital project appraisal.

Common mistake

Mixing one-off and yearly amounts.

Try it in a calculator

Frequently asked questions

BCR above what is good?

Above 1.0 passes; use your organisation’s threshold.

BCR vs NPV?

They give the same accept or reject answer; BCR is a ratio, NPV an amount.