Net present value (NPV)

Net present value is the sum of a project’s cash flows after discounting each one to today. A positive NPV means the project earns more than the discount rate.

Formula

NPV = Σ CFₜ ÷ (1 + r)ᵗ

Worked example

Invest $100,000 and receive $25,000, $30,000, $35,000, $40,000 and $45,000 over five years. At 10%, NPV = $29,079.

Why it matters

NPV states value in money, today.

Common mistake

Using a discount rate that ignores the project’s risk.

Try it in a calculator

Frequently asked questions

What discount rate should I use?

Your hurdle rate or cost of capital, adjusted for risk.

Is a higher NPV always better?

For similar-size, mutually exclusive projects, yes.