Contingency reserve

A contingency reserve is time or money held inside the baseline for identified risks.

Formula

Often sized from the risk register: Σ (probability × impact)

Worked example

Three risks with EMVs of $15,000, $9,000 and $6,000 suggest a contingency of about $30,000.

Why it matters

It lets the project respond to known risks without changing the baseline.

Common mistake

Using a flat percentage with no link to named risks.

Try it in a calculator

Frequently asked questions

Who controls contingency?

Usually the project manager, within the plan.

Is contingency part of BAC?

Yes.