Contingency reserve
A contingency reserve is time or money held inside the baseline for identified risks.
Formula
Often sized from the risk register: Σ (probability × impact)
Worked example
Three risks with EMVs of $15,000, $9,000 and $6,000 suggest a contingency of about $30,000.
Why it matters
It lets the project respond to known risks without changing the baseline.
Common mistake
Using a flat percentage with no link to named risks.
Try it in a calculator
- Contingency Reserve: Estimate risk-based budget reserve.
- Expected Monetary Value: Quantify probability-weighted financial exposure.
Frequently asked questions
Who controls contingency?
Usually the project manager, within the plan.
Is contingency part of BAC?
Yes.