Management reserve

Management reserve is budget held outside the cost baseline for unknown risks, released only with senior approval.

Formula

Project budget = cost baseline + management reserve

Worked example

A $840,000 baseline plus $37,500 management reserve gives a $877,500 budget.

Why it matters

It protects the project from unknown-unknowns without padding the baseline.

Common mistake

Spending it like contingency, without approval.

Try it in a calculator

Frequently asked questions

Is management reserve in BAC?

No.

Who approves its use?

The sponsor or whoever your governance names.