Management reserve
Management reserve is budget held outside the cost baseline for unknown risks, released only with senior approval.
Formula
Project budget = cost baseline + management reserve
Worked example
A $840,000 baseline plus $37,500 management reserve gives a $877,500 budget.
Why it matters
It protects the project from unknown-unknowns without padding the baseline.
Common mistake
Spending it like contingency, without approval.
Try it in a calculator
- Budget at Completion: Develop and review the approved total project budget.
- Contingency Reserve: Estimate risk-based budget reserve.
Frequently asked questions
Is management reserve in BAC?
No.
Who approves its use?
The sponsor or whoever your governance names.