Risk register
A risk register lists identified risks with their probability, impact, owner and planned response.
Formula
Risk score = probability × impact (ordinal scales)
Worked example
A supplier delay rated probability 4 and impact 4 scores 16: high priority.
Why it matters
It is the working record of project risk.
Common mistake
Listing issues, which have already happened, as risks.
Try it in a calculator
- Risk Matrix: Prioritize threats and opportunities by probability and impact.
- Expected Monetary Value: Quantify probability-weighted financial exposure.
Frequently asked questions
Who owns a risk?
A named person accountable for monitoring it and carrying out the response.
How often is it reviewed?
Regularly, and whenever the project changes.