Risk register

A risk register lists identified risks with their probability, impact, owner and planned response.

Formula

Risk score = probability × impact (ordinal scales)

Worked example

A supplier delay rated probability 4 and impact 4 scores 16: high priority.

Why it matters

It is the working record of project risk.

Common mistake

Listing issues, which have already happened, as risks.

Try it in a calculator

Frequently asked questions

Who owns a risk?

A named person accountable for monitoring it and carrying out the response.

How often is it reviewed?

Regularly, and whenever the project changes.