Critical path

The critical path is the longest chain of dependent activities in a schedule. It sets the shortest possible project duration.

Formula

Longest path through the network (activities with zero total float)

Worked example

If path A→B→D takes 3 + 4 + 2 = 9 days and A→C→D takes 7 days, the critical path is A→B→D.

Why it matters

A delay on the critical path delays the project end date by the same amount.

Common mistake

Ignoring near-critical paths, which can become critical after a small slip.

Try it in a calculator

Frequently asked questions

Can there be more than one critical path?

Yes. Paths of equal length are all critical.

Does the critical path change?

Yes, as work finishes early or late.