Total float (slack)

Total float is how long an activity can be delayed without delaying the project end date.

Formula

Total float = late start − early start = late finish − early finish

Worked example

An activity with early start day 3 and late start day 6 has 3 days of total float.

Why it matters

Float shows where the schedule has room and where it has none.

Common mistake

Treating float as owned by one activity. It is shared along a path.

Try it in a calculator

Frequently asked questions

What is zero float?

The activity is on the critical path.

What is negative float?

The schedule cannot meet a constraint without change.