Total float (slack)
Total float is how long an activity can be delayed without delaying the project end date.
Formula
Total float = late start − early start = late finish − early finish
Worked example
An activity with early start day 3 and late start day 6 has 3 days of total float.
Why it matters
Float shows where the schedule has room and where it has none.
Common mistake
Treating float as owned by one activity. It is shared along a path.
Try it in a calculator
- Float / Slack Analysis: Review total and free float across activities.
- Critical Path Calculator: Find the dependency path that determines project duration.
Frequently asked questions
What is zero float?
The activity is on the critical path.
What is negative float?
The schedule cannot meet a constraint without change.