Free float
Free float is how long an activity can be delayed without delaying the early start of any successor.
Formula
Free float = earliest successor early start − this activity’s early finish
Worked example
If an activity finishes on day 7 and its earliest successor can start on day 10, free float is 3 days.
Why it matters
Free float is slack that one activity can use without affecting its neighbours.
Common mistake
Confusing free float with total float. Free float is never larger than total float.