Contingency Reserve vs Management Reserve
Contingency reserve covers identified risks and sits inside the cost baseline. Management reserve covers unknown risks and sits outside the baseline, released only with senior approval.
Side by side
| Contingency reserve | Management reserve | |
|---|---|---|
| Covers | Identified (known) risks | Unidentified (unknown) risks |
| Inside the cost baseline? | Yes | No |
| Part of BAC? | Yes | No |
| Who controls it | Usually the project manager | Senior management or the sponsor |
| Sized from | The risk register | Judgement and organisational policy |
| Used for | Responding to named risks | Unforeseen work within scope |
When to use each
- Use contingency for risks on the register, with a trigger and an owner.
- Use management reserve for events nobody foresaw, with approval.
Example
A $840,000 baseline already includes $90,000 of contingency. A further $37,500 management reserve is held outside it, giving a $877,500 total budget.
Common mistakes
- Putting management reserve into BAC.
- Spending contingency on scope growth.
Frequently asked questions
Is contingency part of the baseline?
Yes.
Does earned value include management reserve?
No. BAC excludes it.