Contingency Reserve vs Management Reserve

Contingency reserve covers identified risks and sits inside the cost baseline. Management reserve covers unknown risks and sits outside the baseline, released only with senior approval.

Side by side

Contingency reserveManagement reserve
CoversIdentified (known) risksUnidentified (unknown) risks
Inside the cost baseline?YesNo
Part of BAC?YesNo
Who controls itUsually the project managerSenior management or the sponsor
Sized fromThe risk registerJudgement and organisational policy
Used forResponding to named risksUnforeseen work within scope

When to use each

  • Use contingency for risks on the register, with a trigger and an owner.
  • Use management reserve for events nobody foresaw, with approval.

Example

A $840,000 baseline already includes $90,000 of contingency. A further $37,500 management reserve is held outside it, giving a $877,500 total budget.

Common mistakes

  • Putting management reserve into BAC.
  • Spending contingency on scope growth.

Frequently asked questions

Is contingency part of the baseline?

Yes.

Does earned value include management reserve?

No. BAC excludes it.