Cycle Time vs Lead Time
Cycle time is the time from starting work on an item to finishing it. Lead time is the time from the request being made to delivery, so it also includes waiting. Lead time is always at least as long as cycle time.
Side by side
| Cycle time | Lead time | |
|---|---|---|
| Starts when | Work begins | The request is made |
| Ends when | Work is finished | The item is delivered |
| Includes waiting in the queue | No | Yes |
| Viewpoint | The team | The customer |
| Reduced by | Smaller items, fewer blockers | Shorter queues, less work in progress |
| Used for | Team forecasting | Service-level commitments |
When to use each
- Use cycle time when you want to improve how the team works.
- Use lead time when you want to know what the customer experiences.
Example
A request waits 6 days, is worked for 4 days and deployed 2 days later. Cycle time is 4 days; lead time is 12 days; flow efficiency is 4 ÷ 12 = 33%.
Common mistakes
- Measuring only development time and calling it lead time.
- Quoting the average rather than a percentile.
Frequently asked questions
What is flow efficiency?
Cycle time divided by lead time.
Which should I forecast with?
Use lead time for customer commitments and cycle time for team planning.