Total Float vs Free Float
Total float is how long an activity can be delayed without delaying the project end date. Free float is how long it can be delayed without delaying the early start of its successor. Free float is never larger than total float.
Side by side
| Total float | Free float | |
|---|---|---|
| Protects | The project end date | The next activity’s early start |
| Formula | LS − ES (or LF − EF) | Successor ES − this EF |
| Shared with other activities? | Yes, along the path | No: it belongs to the activity |
| Zero means | The activity is critical | The next activity is affected by any delay |
| Can be negative? | Yes, with a constraint | Not normally |
| Relationship | Total ≥ free | Free ≤ total |
When to use each
- Use total float to see which activities can slip without moving the end date.
- Use free float to see how far an activity can slip without disturbing the next one.
Example
An activity finishes on day 7 and its successor can start on day 10 (free float 3). If its late finish is day 12, total float is 5.
Common mistakes
- Treating float as spare time for one owner.
- Confusing free float with total float.
Frequently asked questions
Can an activity have total float but no free float?
Yes, when it feeds a successor that has no slack of its own.
What is independent float?
Slack left if predecessors finish as late as possible and successors start as early as possible.