Schedule variance (SV)
Schedule variance is earned value minus planned value. A negative value means less work is done than planned.
Formula
SV = EV − PV
Worked example
PV $50,000, EV $45,000, AC $55,000, BAC $200,000: SV = 45,000 − 50,000 = −$5,000.
Why it matters
SV shows how far progress is from plan, in money.
Common mistake
Reading SV in dollars as if it were days.
Try it in a calculator
- Schedule Variance: Compare earned value with planned value.
- Earned Value Management: Integrate scope, schedule, and cost performance.
Frequently asked questions
Why does SV return to zero at the end?
When work finishes, EV equals PV equals BAC, even if the project finished late.
What is the SV formula?
EV − PV.