Schedule variance (SV)

Schedule variance is earned value minus planned value. A negative value means less work is done than planned.

Formula

SV = EV − PV

Worked example

PV $50,000, EV $45,000, AC $55,000, BAC $200,000: SV = 45,000 − 50,000 = −$5,000.

Why it matters

SV shows how far progress is from plan, in money.

Common mistake

Reading SV in dollars as if it were days.

Try it in a calculator

Frequently asked questions

Why does SV return to zero at the end?

When work finishes, EV equals PV equals BAC, even if the project finished late.

What is the SV formula?

EV − PV.