Variance at completion (VAC)

Variance at completion is the forecast difference between the original budget and the estimate at completion.

Formula

VAC = BAC − EAC

Worked example

BAC $200,000 and EAC $244,444 give VAC = −$44,444, a forecast overrun.

Why it matters

VAC summarises the expected overrun or underrun in one number.

Common mistake

Quoting VAC without the EAC method behind it.

Try it in a calculator

Frequently asked questions

Is a negative VAC always bad?

It signals a forecast overrun; whether it is acceptable depends on reserves and authority to change the baseline.

What is the VAC formula?

BAC − EAC.