Variance at completion (VAC)
Variance at completion is the forecast difference between the original budget and the estimate at completion.
Formula
VAC = BAC − EAC
Worked example
BAC $200,000 and EAC $244,444 give VAC = −$44,444, a forecast overrun.
Why it matters
VAC summarises the expected overrun or underrun in one number.
Common mistake
Quoting VAC without the EAC method behind it.
Try it in a calculator
- Variance at Completion: Forecast the expected overrun or underrun at completion.
- Estimate at Completion: Forecast final project cost from current performance.
Frequently asked questions
Is a negative VAC always bad?
It signals a forecast overrun; whether it is acceptable depends on reserves and authority to change the baseline.
What is the VAC formula?
BAC − EAC.